Impervious Area Calculation

A calculation of how much of a lot is covered by surfaces that prevent water from soaking into the ground.

Site & zoningStormwaterDecks & patios

Applies to

Patios · Driveways · Carports · Garages · Additions

Project example

A new concrete patio plus a carport roof may push a lot over its impervious-area limit even if each piece is separately small.

Also called

impervious coveragestormwater area calculation

Where this term shows up in permit work and how it affects the project

The calculation can determine whether zoning, stormwater, or engineering review is needed and whether a sales promise fits the parcel.

If this term appears in a form, plan comment, or local ordinance, start with the building permit guide, compare it against the zoning permit guide, then use the permit guide directory to find the right local path.

Why it matters for approval

Why impervious area calculation matters in a permit file

An impervious-area calculation converts the site's roofs, pavement, and other regulated surfaces into an auditable area total and percentage. It is useful only when the local definition, zoning-lot area, existing inventory, proposed changes, material classifications, and math all match.

Where it appears in the permit process

  1. Definition and threshold

    The municipality identifies counted surfaces, exclusions, maximum percentage, net-increase threshold, and stormwater triggers.

  2. Existing-area schedule

    The survey or plan inventories each existing roof, drive, walk, patio, pool, and other regulated surface by dimensions and material.

  3. Proposed calculation

    Removed, replaced, and new areas are shown separately before the final square footage and percentage are calculated.

  4. Mitigation or redesign

    An overage or threshold can require smaller improvements, removal, permeable systems, infiltration, detention, engineering, or other local relief.

What you may need

  • Accepted zoning-lot area and current survey or base plan
  • Labeled existing, removed, replaced, and proposed surface areas
  • Dimensioned calculations by material and feature
  • Formula for existing total, net change, final total, and percentage
  • Stormwater, drainage, or permeable-system documentation when triggered

Where to get it or verify it

  • Use the exact impervious definition in the controlling zoning or stormwater ordinance.
  • Use measured plans, survey information, and verified field conditions rather than aerial-image area alone.
  • Use manufacturer and AHJ documentation to support any credit for permeable materials.

Common mistakes that create comments or delays

  • Using building coverage as the impervious total
  • Leaving existing pavement or accessory roofs out of the schedule
  • Counting replacement area as both removed and newly added
  • Providing a percentage without dimensions and intermediate math

What to do next

  1. Confirm the accepted lot area, definition, limit, and review threshold.
  2. Inventory all existing regulated surfaces.
  3. Show removed and proposed areas in a reproducible schedule.
  4. Resolve overages and stormwater triggers before site design is final.